Recent Achievements

  • Beneficiary Identification and Verification:
    • Completed beneficiary identification and registration across five targeted kebeles: Galka’yo, Deyah, Shubo, Dhuurdheer, and Reebo.
    • A house-to-house independent beneficiary verification process was conducted, leading to the disqualification and replacement of 19 beneficiaries:
      • Reebo: 6 beneficiaries
      • Dhuurdheer: 4 beneficiaries
      • Shubo: 4 beneficiaries
      • Galka’yo/Deqsuge: 3 beneficiaries
      • Deyah/Hara’ad: 2 beneficiaries
    • Reasons for Replacement:
      • Double registration within a household
      • Failure to meet selection criteria
      • Non-residency in the target areas
      • Relationship with members of the beneficiary selection committee
  • Verification Results:
    • Out of the 1000 targeted households, 827 households (82.7%) were verified through house-to-house visits, while the remaining 173 households (17.3%) were verified using community-based methods due to flooding-related access challenges.
  • Field Visit & FSP Selection:
    • The IOM support team visited the project areas, assessed the interventions, and engaged with local stakeholders.
    • Awash Bank was selected as the Financial Service Provider (FSP) for the MPCA program based on their experience and capacity.

Plan for Next Week

  • Sign an agreement with Awash Bank as the FSP.

Challenges

  • Flooding Impact:
    • Access to some areas was restricted due to flooding caused by the Shabale River overflow, requiring alternative community-based verification methods for certain households.
  • Infrastructure Issues:
    • Poor road infrastructure and remote kebele locations further complicated access.

Stay with us for more updates.